UPSC Prelims 2011 CSAT question 35

A contract on construction job specifies a penalty for delay in completion of the work beyond a certain date is as follows : ₹ 200 for the first day, ₹ 250 for the second day, ₹ 300 for the third day etc., the penalty for each succeeding day being ₹ 50 more than that for the preceding day. How much penalty should the contractor pay if he delays the work by 10 days ?