AI Data Centres Strain Grids
3.1 Economics, The Hindu, 2026-10-11
NERPC told that PGCIL's estimated cost of upgrading SCADA/EMS at State Load Despatch Centres rose from ₹521 crore to about ₹688 crore due to AI-driven hardware demand. Regional power committees flag data-centre ramping risks, including Deviation Settlement Mechanism penalties for slow-ramping generators. AIDA says 1-2 GW per year incremental demand is manageable. Noida has 125 MW operational capacity, with over four times in the pipeline. WRPC recorded 32 MW data-centre load shedding on June 12. CERC rules make data-centre operators bear transmission extension costs.