(e) Cost-Benefit Analysis has been developed to make expenditure decision more appropriate. Explain the statement with your comments.
Apoorva Agrawal, AIR 65, 2024
Cost - benefit analysis is a tool used in policy making to evaluate the different development projects and make the best-choice.
- NPV analysis (Net Present Value) is an import type of cost - benefit analysis. It calculates the net present value of expected benefit stream and compares it to the cost of the project - For example, if cost of project is C. Benefit accrues in each period as B1, B2, B3, ...... Now, Net Benefit = Benefit - Cost = NPV of Benefit stream - Cost
NPV = B1 + B2/(1+r) + B3/(1+r)^2 + ... + Bn/(1+r)^(n-1) - C
where r is the rate of discount - If NPV > 0, benefit stream exceeds cost and thus, the project is viable
Problems in Cost- Benefit Analysis 1. Availability of appropriate data for cost & benefits 2. Accurate forecasting of future pay off stream 3. Informal markets may make finding true cost of land, capital, labour difficult
Way Ahead 1. Using 'shadow-prices' in case actual prices are unavailable 2. Data-analytics tools like AI, softwares, etc to be used 3. Open-data led governance models to ensure proper use of public data for precise decision making
Thus, cost - benefit-analysis can provide of benefits of better expenditure & development planning for prudent use of public funds