Q.7) Prateek Kumar, the Project Manager, is in charge of the construction of a highly anticipated highway that is expected to drive regional development. The project aims to enhance connectivity, boost trade, and create substantial employment opportunities. Given its importance, it has become a focal point for the ruling party, which is actively promoting it as a symbol of progress ahead of the upcoming state elections next year. The timely completion of the highway is crucial, as the Chief Minister is scheduled to inaugurate it upon completion. This has led to added pressure on Prateek and his team to meet the approaching deadline, which is set for next month. During a routine inspection, Prateek discovers that a particular stretch of the highway has been built with substandard materials. This section fails to meet the required safety and durability standards, posing a serious threat to public safety and lives. If left unresolved, the compromised quality could lead to accidents, undermining both the project's credibility and the government's promises for safe and reliable infrastructure. Concerned, Prateek raises the issue with the contractor, but the contractor downplays the severity, claiming that minor adjustments will fix the problem without causing major delays. In a subsequent team meeting, some senior members suggest that Prateek overlook the quality concerns to ensure the project remains on schedule. They argue that the majority of the highway meets standards and emphasize the severe economic and political consequences of delays. With elections approaching, they stress the importance of the Chief Minister's inauguration as a key political event. They warn that any delay could damage the ruling party's image, harm its electoral prospects, and potentially have repercussions for the team and the organization. Later, the contractor privately approaches Prateek with a substantial bribe, urging him to ignore the issue and allow the project to proceed. The contractor justifies his actions by citing financial pressures and the need to complete the project on time. Prateek is an honest and upright officer, but he understands that addressing the problem would delay the project, making it impossible to meet the deadline. a. Discuss the ethical issues involved in the case. b. Under the given conditions, what are the options available to Prateek as the Project Manager? Critically evaluate each of the options. c. What option should Prateek adopt and why?

Monika Srivastava, AIR 16, 2025

The above case study highlights ethical issues associated with Quality of Public Services like Infrastructure development. Recent cases of Bridge collapses in Bihar and Morbi Bridge shattering has caused loss of lives.

a) Ethical Issues Involved

1. Development of Region and Timely Completion of Projects for welfare of all (utilitarianism) -> Delays can hinder this 2. Pressure on Prateek <-> Impartiality and Non-Partisanship as key values 3. usage of Substandard materials in Construction <-> violation of social contract (Poor Quality of Service delivery) 4. Misutilisation of Public Resources <-> taxpayers money 5. lack of Accountability and ownership of contractor <-> Professional duty compromised (Against duty based ethics) 6. Suggestion by senior members to overlook <-> Systemic corruption in Team 7. Importance of CM Inauguration <-> Preference of Political means to achieve ends (Kantian ethics) 8. offering of Bribe to Prateek <-> Corruption and Quid Pro Quo attitude 9. Crisis of conscience with Prateek <-> mental discomfort 10. Violation of Constitutional morality and Rule of law

b) Options available to Prateek as manager

Option I - Accept Bribe and overlook the issues - Pros: (i) Timely completion (ii) Loyalty to political masters - Cons: (i) Professional duty compromised (ii) collusive corruption (iii) Safety and Threat to life

Option II - Deny the Bribe outrightly and flag concerns with higher-ups - Pros: (i) Professional Integrity (ii) Duty based ethics (iii) Virtuous character (iv) zero Tolerance to corruption (v) consumer safety first - Cons: (i) Delays in project completion (ii) Retaliation from political executive (iii) Delay in CM event

Option III - Resign from the job - Pros: (i) No moral dilemma - Cons: (i) Loss of inner peace (ii) Does not solve the problem

Option IV - Use persuasion and objectivity to raise concerns with Senior members, with potential repercussions in future - Pros: (i) Persuasion might change attitude of others (ii) Team effort for Project completion - Cons: (i) Might be seen as overstepping (ii) Ignorance by others

c) Course of action that Prateek should adopt

should be based on - - Professional Integrity and Duty - Standards of Infrastructure development - Company commitments towards Public Service - Constitutional values

Steps that Prateek should take

1. Speak to senior members and flag future possibilities of Bridge collapse -> Quote recent Scrutiny and Suspensions of engineers involved in Morbi collapse -> Short Term gains not to be preferred over long term vision 2. use data based objective assessment and use pathos, logos, emos for effective persuasion -> Change Seniors' attitude 3. Exhaust all Internal mechanism to raise concern, go through chain of command till Board of Directors -> courage of conviction to stand up for what is right 4. In case all above fails, report to media about potential impact and harm associated with project -> Collect required evidence and data to back up -> Seek professional counseling to maintain calm -> Raise concern against contractor and his move to bribe

Long Term Measures

1. Audit mechanism by Third party to assess Quality 2. Citizen charter and Defined Quality of service deliver -> Sevottam Model 3. Capacity Building and Code of Ethics 4. zero Tolerance to corruption 5. Whistle Blower Protection

Eminents like Satyendra Dubey and Manjunath Shanmugam sacrificed their lives to keep up with highest standards of moral integrity. They are an inspiration to managers like Prateek.